PS 428 Booster Pump Station

  • Sep 28, 2011

This project involves the installation of a wastewater booster pump station along 41st Avenue East between 67th Street Court East and I-75. This project will reduce the existing line pressures and increase system reliability.

--
Contractor:
Westra Construction, Inc.
Construction Cost:
$1,707,000.00
Start date:
Feb 11, 2011 3:10:19 PM
Completion date:
Feb 11, 2012 3:10:26 PM
Contact Information:
Anthony Benitez, 941-708-7450 Ext. 7333, anthony.benitez@mymanatee.org