Cortez Estates - Potable Waterline Upgrade

  • Nov 18, 2010

The scope of work includes the installation of approximately 4,188 linear feet of 6-inch waterline and approximately 969 linear feet of 8-inch waterline to replace existing waterlines in the area. Four fire hydrants will be installed as well as approximately 70 service connections.

This project is located on the following streets:

 
56th Street West
South of Cortez Road to 58th Street West
57th Street West
South of Cortez Road to 58th Street West
58th Street West
South of Cortez Road to the dead end

 

Contractor:
Cimmaron Construction, Inc.
Construction Cost:
$311,000
Start date:
Jul 29, 2010 12:00:00 AM
Completion date:
Apr 11, 2012 8:59:08 AM
Contact Information:
Walter Sowa III